Chapter8.CostEstimationandBudgeting.pptx

Project Management: Achieving Competitive Advantage
Fifth Edition
Chapter 8
Cost Estimation and Budgeting

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

If this PowerPoint presentation contains mathematical equations, you may need to check that your computer has the following installed:
1) MathType Plugin
2) Math Player (free versions available)
3) NVDA Reader (free versions available)
1

Learning Objectives
8.1 Understand the various types of common project costs and key differences between them.
8.2 Apply common forms of cost estimation for project work, including ballpark estimates, definitive estimates, parametric estimates, and learning curve.
8.3 Apply top-down, bottom-up, activity-based, and time-phased budgeting procedures for cost management.
8.4 Recognize the appropriateness of applying contingency funds for cost estimation.

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

P M B o K Core Concepts
Project Management Body of Knowledge (P M B o K) covered in this chapter includes:
Plan Cost Management (P M B o K 7.1)
Estimate Costs (P M B o K 7.2)
Determine Budget (P M B o K 7.3)
Control Costs (P M B o K 7.4)

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Cost Management
Cost management has been defined to encompass data collection, cost accounting, and cost control.
Cost accounting and cost control serve as the chief mechanisms for identifying and maintaining control over project costs.
Cost estimation processes create a reasonable budget baseline for the project.

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Common Sources of Project Cost
Labor
Materials
Subcontractors
Equipment and facilities
Travel

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Types of Costs
Direct Versus Indirect
Recurring Versus Nonrecurring
Fixed Versus Variable
Normal Versus Expedited

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Figure 8.2 Project Price Breakdown

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Table 8.2 Cost Classifications

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Cost Estimation
Ballpark ( of magnitude)

Comparative

Feasibility

Definitive

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Learning Curves
Each doubling of output results in a reduction in time to perform the last iteration.

Where :
Yx = the time required for the x unit of output
a = the time required for the initial unit of output
X = the number of units to be produced
b = learning curve slope

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Figure 8.6 Unit Learning Curve Log-Linear Model

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Software Project Estimation—Function Points
Function Point Analysis is a system for estimating the size of software projects based on what the software does.
Function Points are a standard unit of measure that represents the functional size of a software application.

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Figure 8.7 Software Project Development Activities as a Function of Size

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Table 8.4 Complexity Weighting Table for Function Point Analysis

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Table 8.5 Function Point Calculations for Restaurant Re System

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Problems with Cost Estimation
Low initial estimates
Unexpected technical difficulties
Lack of definition
Specification changes
External factors

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Creating a Project Budget
The budget is a plan that identifies the resources, goals, and schedule that allows a firm to achieve those goals.
Figure 8.8 The Relationship Among W B S, Scheduling, and Budgeting

Top-down
Bottom-up
Activity-based costing (A B C)

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Activity-Based Costing
Projects use activities and activities use resources.
Assign costs to activities that use resources.
Identify cost drivers associated with this activity.
Compute a cost rate per cost driver unit or transaction.
Multiply the cost driver rate times the volume of cost
driver units used by the project.

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Table 8.6 Sample Project Budget

Activity Direct Costs Budget Overhead Total Cost

Survey 3,500 500 4,000

Design 7,000 1,000 8,000

Clear Site 3,500 500 4,000

Foundation 6,750 750 7,500

Framing 8,000 2,000 10,000

Plumb and Wire 3,750 1,250 5,000

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Table 8.7 Sample Budget Tracking Planned and Actual Activity Costs

Activity Direct Costs Budget Overhead Total Cost

Survey 4,000 4,250 250

Design 8,000 8,000 – 0 –

Clear Site 4,000 3,500 (500)

Foundation 7,500 8,500 1,000

Framing 10,000 11,250 1,250

Plumb and Wire 5,000 5,150 150

Total 38,500 40,650 2,150

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Table 8.8 Example of a Time-Phased Budget

Activity January February Months March April May Total by Activity

Survey 4,000 Blank Blank Blank Blank 4,000

Design Blank 5,000 3,000 Blank Blank 8,000

Clear Site Blank 4,000 Blank Blank Blank 4,000

Foundation Blank Blank 7,500 Blank Blank 7,500

Framing Blank Blank Blank 8,000 2,000 10,000

Plumb and Wire Blank Blank Blank 1,000 4,000 5,000

Monthly Planned 4,000 9,000 10,500 9,000 6,000 Blank

Cumulative 4,000 13,000 23,500 32,500 38,500 38,500

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Figure 8.9 Cumulative Budgeted Cost of the Project

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Budget Contingencies
The allocation of extra funds to cover uncertainties and improve the chance of finishing on time.
Contingencies are needed because:
Project scope may change
Murphy’s Law is present
Cost estimation must anticipate interaction costs
Normal conditions are rarely encountered

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Benefits to Contingency Funding
Recognizes future contains unknowns
Adds provision for company plans for an increase in project cost
Applies contingency fund as an early warning signal to a potential overdrawn budget

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Summary
Understand the various types of common project costs and key differences between them.
Apply common forms of cost estimation for project work, including ballpark estimates, definitive estimates, parametric estimates, and learning curve.
Apply top-down, bottom-up, activity-based, and time-phased budgeting procedures for cost management.
Recognize the appropriateness of applying contingency funds for cost estimation.

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Copyright

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
±
30%
±
15%
±
10%
±
5%
=

b
x
YaX
(
)
= log learning %log(2)

Place your order
(550 words)

Approximate price: $22

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency
Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

Each paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.

Read more

Free-revision policy

Thanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.

Read more

Privacy policy

Your email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.

Read more

Fair-cooperation guarantee

By sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.

Read more

Order your essay today and save 30% with the discount code HAPPY