PRJ656

Week 3 – The Scott Project

Project Management Integration Framework – PRJ656

Anthony Burkett, Rodney Hodge, Herbert Green, Jonathan Rhys Jones

Grantham University

PRJ656

Project Charter
Project Title: The Scott Project

Project Start Date: January 3, 2010 Project End Date: November 1, 2010

Budget Information: The Scott Project has an estimated total labor cost of $250K per month throughout the life of the project.
The initial estimate is based on a total of 2,080 per month at $120 per person.

Project Manager: Jerry Dunlap/ Phone: 321-456-7891/ Email: [email protected]

Project Objectives:
– Implement a new product for Scott Corporation that can easily transition into their strategic plan.
– Bring value to Scott Corporation.
– Increase trust between Park Industries & Scott Corporation
– Develop opportunities for follow-on work over the next several years.

Main Project Success Criterion: Customer satisfaction: This project should initiate future sole-source contracts between Scott
Corporation and Parks Industries.

Approach: Due to having a well experienced team however, faced with possible time constraints, the agile methodology is
more suitable for this project. The agile approach also gives room for flexibility and quicker delivery.

Sequence of Approach
1) Determine Requirements: Get a detailed understanding of the project requirements.
2) Development: Design, add functionality and test the project.
3) Release: Incremental release of the product for customer feedback.
4) Accept: Customer accepts the project
5) Deploy to Customer: Project is approved and delivered.
5A) If not accepted, changes will be implemented, and the project will enter the next development iteration.

Roles & Responsibilities (Partial List)

Name Role Position

Jason Scott Jason Scott CEO Scott Corporation

Joseph Park Joseph Park Budget Allocation General Manager, Park Industries

Frank Howard Frank Howard Liaison Project Management Division Head

Jerry Dunlap Jerry Dunlap Project Manager Project Manager

6 x Full-Time Employees All Employees Team Members Project Officers

4 x Full-Time Employees All Employees Team Members Functional Team Members

4 x Part-Time Employees All Employees Team Members Functional Team Members

Sign-Off: By signing this document, Scott Corporation and Park Industries approve this project charter.

Management Plan

I. Overview

mailto:[email protected]

PRJ656

a. Project name: The Scott Project

b. Purpose:
i. The goals of the project: To develop a new product for the

Scott Corporation.
ii. Strategic reason for the project: Satisfaction of this project

offers tremendous opportunities for follow-on work over the
next several years.

iii. Time estimate: Approximately 10 months.
iv. Cost estimate: $240,000 per month of project/ $2.5M

Overall

c. Sponsor
i. Name: Jason Scott

ii. Title: The Scott Corporation CEO
iii. Contact information: 321-456-7890

d. Team/Stakeholders

Name Title Phone Email

Jason Scott Sponsor/CEO 321-456-7890 [email protected]

Jerry Dunlap Project Manager 321-456-7891 [email protected]

Joseph Park Budget Allocation 321-456-7892 [email protected]

Frank Howard Liaison 321-456-7893 [email protected]

6 x Full Time
Employees

Project Officers 321-456-7894 [email protected]

4 x Full Time
Employees

Functional Team Members 321-456-7895 [email protected]

4 x Part Time
Employees

Functional Team Members 321-456-7896 [email protected]

e. Deliverables

Product Description

mailto:[email protected]

mailto:[email protected]

mailto:[email protected]

mailto:[email protected]

mailto:[email protected]

mailto:[email protected]

mailto:[email protected]

PRJ656

Successful R&D The Research and Development needs to be completed to 100%
for the product.

New product New product to bring value to the Scott Corporation.

f. A list of important reference materials:
i. Scope management plan: The scope creates the new

product for the Scott Corporation and the planning for
developing follow-on opportunities for work over the next
several years.

g. A list of definitions and acronyms, if appropriate:

Term Definition

R&D Research and Development

Bath Tub Timeframe of inactivity of a project prior to the next phase
beginning.

II. How the project is organized

a. Project responsibilities:

i. Project Manager – The Project management will coordinate,
synchronize, and integrate all activities in this project. They are
responsible for the overall delivery of the service to the
customer and ensuring it is within scope, budget, and on time.

ii. Requirement Analyst – Will adhere to the project scope as
prescribed by the customer and will ensure that all perimeters of
the service to the customer are answered and that specifications
are identified before project is initiated.

iii. Research and Developers – Will conduct the scientific research
to create the product.

iv. Software Developers – Will develop the coding needed to
continue the production of the product.

III. Management and technical approaches:

PRJ656

a. Management objectives: The main approach will be to deliver the
product in an effective way that focuses on Customer Satisfaction. The
focus of this product is to deliver a product to create a relationship
between both organizations that fosters follow-on work for the next
several years.

b. Project controls: There will be several project management controls
built in. Most prominently is testing starting mid process of research
and development. As this is the main effort for this project, the focus of
the product is to create the product in alignment with the customer
requirements.

c. Risk management: The major risk with this project is delivering a
product that is not to the customer standards. The stakeholder/customer
will be heavily involved throughout the research and development of
the product to ensure the highest level of satisfaction and promote a
relationship between the two organizations. Additionally, efforts must
be made to ensure that the “Bath Tub” period does not negatively
impact the project. Maintaining the same project staff throughout the
project will increase the chance of being successful. If the same staff
isn’t available, the risks will be mitigated by ensuring detailed
documents are maintain discussing project successes and other best
practice knowledge.

d. Project staffing: This project will be a mixed staff of project managers
and team members both on a full-time and part-time basis. Since the
workload is up and down, the staff members will be matrixed to this
project as it allows them the flexibility to work on other projects while
the workload is low for the Scott Project.

IV. Project schedule

a. Summary schedule: January 3, 2010, through November 1, 2010

V. Budget

a. Summary budget: The overall budget for this project is approximately
$250,000 per month with a total of ~$2.5M over the 10-month duration
of the project.

b. Detailed budget: The workload fluctuates however the manpower level
will roughly equal to 2,080 labor hours per month. Each labor hour will
be incurrent at a cost of $120.00 per person, at a full rate.

PRJ656

c. Other budget-related information: The Scott Corporation has a cash
flow issue and the follow-on work post this project, will have to be
significant to the cut in budget to maintain team members and project
managers for follow on work. The bathtub budget after this project is
~$200,000.

References

Schwalbe, K. (2015). Information Technology Project Management. (8th Ed). Boston, MA:

Cengage Learning.

PRJ656

I. Overview
II. How the project is organized
III. Management and technical approaches:
IV. Project schedule
V. Budget

Place your order
(550 words)

Approximate price: $22

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency
Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

Each paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.

Read more

Free-revision policy

Thanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.

Read more

Privacy policy

Your email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.

Read more

Fair-cooperation guarantee

By sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.

Read more

Order your essay today and save 30% with the discount code HAPPY