1) The following information is taken from the production budget for the first quarter:
Beginning inventory | 3,200 units |
Budgeted sales for the quarter | 335,000 units |
How many units should be produced during the quarter if the company desires 3,900 units available to start the next quarter?
2) Problem #1 – 16 points
Star, Inc. produces several models of clocks. An outside supplier has offered to produce the commercial clocks for Star, Inc for $15 each. Star, Inc needs 600 clocks annually. If Star, Inc. chooses to make its commercial clocks, the following unit costs for producing commercial clocks are provided:
Unit costs | |
Direct materials | $2 |
Direct labor | 4 |
Variable overhead | 3 |
Fixed overhead | 10 |
Required: If Star, Inc. chooses to the clocks from the outsider supplier, 80% of fixed overhead costs is UNAVOIDABLE. Prepare an incremental analysis which shows the effect of the make-or- decision. Copy and paste the table and questions below into the answer box and use it to complete the incremental analysis.
Make | ||
Direct Material | ||
Direct Labor | ||
Variable Overhead | ||
Fixed Overhead | ||
Purchase Price | ||
Total Costs |
Star, Inc. should make or the commercial clocks?_________________________
Why?____________________________________________________________________
Problem #2– 15 points
Modern Design provided the following budgeted information for June through August:
June | July | August | |
Projected merchandise purchase | $10,400 | $12,300 | $11,500 |
Projected credit sales | $9,600 | $12,000 | $8,000 |
The company pays 10% of merchandise purchases in the month of purchasing, 80% in the following month of purchasing, and 10% in the second month following purchasing.
Required: How much are budgeted cash payments for June, July and August?
Copy and paste the questions below into the answer box and enter your answer. (show your calculation steps!!)
Cash payments for June=______________________
Cash payments for July=______________________
Cash payments for August=_______________________
Problem #3 – 15 points
During June, Joss Co. incurs 900 hours of direct labor at an hourly cost of $15 in producing 320 units of its finished product. Joss’s standard labor cost per hour is $22 and standard hour used to produce one unit of finished product is 3 hours.
Required: Compute the total, price, and quantity labor variances for Joss Co. during June
Copy and paste the questions below into the answer box and enter your answer. (show your calculation steps!!)
Total labor variance=_________________
Labor price variance =________________
Labor quantity variance=________________
Problem #3 – 15 points
During June, Joss Co. incurs 900 hours of direct labor at an hourly cost of $15 in producing 320 units of its finished product. Joss’s standard labor cost per hour is $22 and standard hour used to produce one unit of finished product is 3 hours.
Required: Compute the total, price, and quantity labor variances for Joss Co. during June
Copy and paste the questions below into the answer box and enter your answer. (show your calculation steps!!)
Total labor variance=_________________
Labor price variance =________________
Labor quantity variance=________________
Problem #3 – 15 points
During June, Joss Co. incurs 900 hours of direct labor at an hourly cost of $15 in producing 320 units of its finished product. Joss’s standard labor cost per hour is $22 and standard hour used to produce one unit of finished product is 3 hours.
Required: Compute the total, price, and quantity labor variances for Joss Co. during June
Copy and paste the questions below into the answer box and enter your answer. (show your calculation steps!!)
Total labor variance=_________________
Labor price variance =________________
Labor quantity variance=________________
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more